我列出一个有价值的例子与大家共享.
"Requirement: The organization shall promote supplier monitoring of the performance of their manufacturing processes.
Failure: When supplier submitted concession for NG product, root cause and corrective action was not always required for suppliers.
Evidence: P/n#XXXX 18000pcs not conforming drawing. "
cause:
a.The requirement of TS and quality manual is not understand well; b.No detail method to monitor supplier's manufacturing process performance defined in QP/WI.
Action plan:
1.Study the requirement of TS and quality manual; 2.Add detail method to monitor supplier's manufacturing process performance in QP on supplier & WI on SNCR,require that for material concession,supplier should submit SNCR with root cause and corrective action to improve process performance ; 3.implement the QP /WI .
13 个回复
richwell (威望:5)
赞同来自:
"Requirement: The organization shall promote supplier monitoring of the performance of their manufacturing processes.
Failure: When supplier submitted concession for NG product, root cause and corrective action was not always required for suppliers.
Evidence: P/n#XXXX 18000pcs not conforming drawing. "
cause:
a.The requirement of TS and quality manual is not understand well; b.No detail method to monitor supplier's manufacturing process performance defined in QP/WI.
Action plan:
1.Study the requirement of TS and quality manual; 2.Add detail method to monitor supplier's manufacturing process performance in QP on supplier & WI on SNCR,require that for material concession,supplier should submit SNCR with root cause and corrective action to improve process performance ; 3.implement the QP /WI .