Xbar-R控制图的分析,热心人请解惑

下面是我刚在网上看到的题目与解答,不太理解为什么答案是2),我觉得2,3,4都是对的,即这三种顺序都不对,请帮忙看看,不知是我对英语题意理解错误还是怎么回事。

Arrange the applicable statements in order as one has to do to analyze X-bar R chart.
i) Obtain the customer specification limits for calculating control limits.
ii) Look at Range charts, if it is out of control, X-bar chart has no value.
iii) Review X-bar chart with respect to control limits and carry out Run tests.
iv) Calculate DPMO, after locating points beyond specification limits from X-bar R chart.

1 i), ii), iii), iv)
2 ii), iii); i) and iv) are not applicable.
3 ii), iii), iv); i) is not applicable.
4 i), ii), iii); iv) is not applicable.

Explanation:
Always analyze the Range chart first. The control limits of X-bar chart is taken from the average Range, so if the Range chart is out of control, then the control limits of X-bar is of no value. Never compare the points of X-bar chart control limits with respect to specification limits.
对“好”的回答一定要点个"赞",回答者需要你的鼓励!
已邀请:

gongyong1981112 (威望:2) (湖北 荆州)

赞同来自:

Then even one specific point is out of control limit, while maybe meet specification.转载!!!!!!11111111111111

5 个回复,游客无法查看回复,更多功能请登录注册