[原创]工程能力分析&正态性验证
1.工程能力分析前做正态性验证。
P-value>0.05,是正态分布
P-value<0.05,不是正态分布
2.工程能力分析得出工程能力指数。
CP :短期工程能力指数
CPK:短期工程能力指数(考虑平均值偏移)
PP :长期工程能力指数
PPK:长期工程能力指数(考虑平均值偏移)
3.算出短期工程能力和长期工程能力及工程能力变动。
ZST=3  CP ;
ZLT=3  PPK ;
Zshift= ZST  ZLT
4.做出4-Block图,决定改善方向。
A:技术管理都需要改善
B:技术优秀,管理需要改善
C:管理优秀,技术需要改善
D:世界一流水平
P-value>0.05,是正态分布
P-value<0.05,不是正态分布
2.工程能力分析得出工程能力指数。
CP :短期工程能力指数
CPK:短期工程能力指数(考虑平均值偏移)
PP :长期工程能力指数
PPK:长期工程能力指数(考虑平均值偏移)
3.算出短期工程能力和长期工程能力及工程能力变动。
ZST=3  CP ;
ZLT=3  PPK ;
Zshift= ZST  ZLT
4.做出4-Block图,决定改善方向。
A:技术管理都需要改善
B:技术优秀,管理需要改善
C:管理优秀,技术需要改善
D:世界一流水平
没有找到相关结果
已邀请:
2 个回复
ysliu (威望:0) (台湾 台北) 服务业 经理 - ysliu
赞同来自:
Your customer has asked you to report the Cpk of the product you are sending. You know that to compute the Cpk, you need to have the product specifications, and that you need to have the mean and sigma. As you gather the information, someone asks, "which sigma do they want?"
You know that Cpk is calculated by dividing by 3 sigma. But which sigma should you use, estimated or calculated? Which is correct? Which would you report? Naturally, most of us would use the sigma that makes the Cpk look the best. But the sigma that makes the Cpk look best may not accurately reflect what you or your customer need to know about the process.
Confusion over calculating Cpk by two different methods is one reason that a new index, Ppk, was developed. Ppk uses the calculated sigma from the individual data.
Given that Ppk uses the calculated sigma, it is no longer necessary to use the calculated sigma in Cpk. The only acceptable formula for Cpk uses the estimated sigma.
In 1991, the ASQC/AIAG Task Force published the "Fundamental Statistical Process Control" reference manual, which shows the calculations for Cpk as well as Ppk. These should be used to eliminate confusion about calculating Cpk.
So which value is best to report, Cpk or Ppk? Although they show similar information, they have slightly different uses.
Estimated sigma and the related capability indices (Cp, Cpk, and Cr) are used to measure the potential capability of a system to meet customer needs. Use it when you want to analyze a system's aptitude to perform.
Actual or calculated sigma (sigma of the individuals) and the related indices (pp, Ppk, and Pr) are used to measure the performance of a system to meet customer needs. Use it when you want to measure a system's actual process performance.